Supply chain management and lean concept in construction: a case of Ghanaian building construction industry

   | Dec 31, 2019

Cite

Characteristics of case projects

Project nameContract sum (US$)Contractor
Construction of 4-Storey Examination Block5,500,000Berock Ventures Limited
Construction of 4-Storey N-Block for the College of Engineering6,200,000Berock Ventures Limited
Construction of VIP Ward for KNUST Hospital2,200,000Stivo Company Limited
Construction of 3-Storey Computer Laboratory and Canteen Block for KNUST JHS1,500,000Asib Company Limited

Level of coordination and collaboration among industry players

NMeanStandard deviationStandard error mean
Consultants634.480.6020.131
Subcontractors633.900.9440.206
Major suppliers634.140.9100.199
Clients634.670.4830.105

Coordination in planning of activities

NMeanStandard deviationStandard error mean
Consultants634.570.7460.163
Subcontractors603.651.1370.254
Major suppliers603.301.3800.309
Clients604.201.0050.225

Respondents information

FrequencyPercent
Profession of respondents
Quantity surveyor2438
Architect2438
Engineer35
Project manager1219
Total63100
Academic qualification
MSc/MPhil/MTech2540
BSc/BEng/BTech3657
HND23
Total63100
Years of experience
Below 5 years23
5–10 years1829
10–15 years1930
15–20 years1219
Above 20 years1219
Total63100

Sources of waste

ItemNMeanStandard deviationStandard error mean
ADelays in arrival of workers, plant and materials633.76190.700340.15283
BSlow decision-making and instructions by consultants633.61900.740010.16148
CWaste of materials633.52380.749600.16358
DShortage of materials633.52380.872870.19048
EInefficient movement of workers633.38100.804750.17561
FPoorly scheduled delivery of materials to site633.28570.845150.18443
GAccidents633.23810.624880.13636
HExcess materials in store633.19050.928390.20259
IWaiting and idling633.19050.928390.20259
JDouble handling of materials633.14290.910260.19863
KUse of materials over and above specifications633.14290.963620.21028
LDeterioration of materials633.09520.768420.16768
MRework633.04760.804750.17561
NUnnecessary or not enough information flow633.0000.894430.19518
OWaste of space on-site632.95240.740010.16148
PDefects632.95240.740010.16148
QWork not done632.95240.864650.18868
ROver allocation of materials to an activity632.95240.973460.21243
SUnnecessary work632.90480.889090.19401
TPoor quality of materials632.85710.792820.17301
UPoor storage of materials632.80950.749600.16358
VWorkers performing activities well below their capabilities632.80950.872870.19048
WAbnormal use of equipment and tools632.71430.845150.18443
XInadequate storage spaces632.71430.845150.18443

Communication and information sharing

NMeanStandard deviationStandard error mean
Consultants574.680.4780.110
Subcontractors604.300.5710.128
Major suppliers604.250.5500.123
Clients634.430.7460.163