Cost and time analysis for traditionally procured public projects

S/nProject typeFC. (mill.)IC. (mill.)Dev.% Dev.FT. (weeks)IT. (weeks)Dev.% Dev.
1Educational building45.039.06.015.445301550.0
2Educational building18.011.56.556.52824416.7
3Social building600.0600.00.00.096762026.3
4Residential116.093.023.024.746361027.8
5Residential2.32.30.00.0101000.0
6Residential5.75.70.00.0121200.0
7Residential5.65.60.00.0151500.0
8Offices37.533.04.513.63430413.3
9Educational building501.3395.5105.726.748351337.1
10Educational building150.0150.00.00.072522038.5
11Residential13.513.50.00.0321517113.3
12Offices55.450.74.79.336241250.0
Average12.512.21031.1

Factors influencing the choice of procurement method used in public project delivery

FactorsMin.Agen.LG.Tert.OverallANOVA
MISRkMISRkMISRkMISRkMISRkFSig.
Price competition - need to achieve value for money and public accountability4.2713.7543.4024.2713.9811.6220.199
Speed - in all phases of the project4.1323.50103.6014.0023.8620.6540.585
Time certainty - ability to complete project within the agreed duration4.0743.8633.1074.0023.7931.8690.151
Complexity of the project4.1323.6373.2063.9143.7742.0710.119
Flexibility - ability to accommodate changes during design and construction phases3.8674.0013.2253.6483.6951.3430.275
Quality - the need to fulfil client’s expectation of essential project characteristics3.9363.7163.1073.7363.6461.8090.162
Familiarity - based on previous experience3.8083.43123.3333.7363.6270.5610.644
Simplicity - in terms of activities, process and procedure4.0743.5793.1073.36123.5882.4300.080
Price certainty - the ability to keep expenditure within budgeted estimate3.8083.50102.90103.9143.5791.8220.159
Government policy - on using a particular procurement route3.60103.6372.90103.6483.45101.3660.267
Dispute resolution and arbitration3.36124.0013.3332.91133.34112.4060.083
Responsibility - the need to be involved in and to be kept informed about the project through its life3.40113.7552.80133.40113.33121.1050.359
Risk allocation - knowledge on how and to what degree uncertainties/risks have been passed to or shared among parties3.33133.14132.90103.44103.22130.9060.448

Summary of the cost performance of public building projects, analyzed using the paired-samples t-test

Procurement typeOverall deviation (million)Overall % deviationStd. deviationStd. error meanTDfSig. (two-tailed)
Traditional12.512.230.18.71.44110.177
Direct labour1.08.82.90.91.13110.281
Management procurement115.28.8382.6110.51.04110.319

Summary of the time performance of public building projects using the paired-samples t-test

Procurement typeOverall deviationOverall % deviationStd. deviationStd. error meanTDfSig. (two-tailed)
Traditional1031.1824.296110.001**
Direct labour424.7412.974110.013**
Management procurement1447.41752.845110.016**

Cost and time analysis for management-procured public projects

S/nProject typeFC. (mill.)IC. (mill.)Dev.% Dev.FT. (weeks)IT. (weeks)Dev.% Dev.
1Educational building67.063.04.06.3726757.5
2Social building3,213.01,883.01.370.66600.0
3Educational building29.629.60.00.0242400.0
4Educational building110.0110.00.00.032201260.0
5Social building69.469.40.00.053302376.7
6Social building121.1121.10.00.03021942.9
7Health centre250.0217.033.015.232211152.4
8Health centre172.7160.212.47.83224833.3
9Educational building158.5158.498.20.11145262119.2
10Social building54.051.12.95.7242400.0
11Residential69.769.70.00.0422022110.0
12Residential245.0245.00.00.040241666.7
Average115.28.81447.4

Cost and time analysis for direct labour-procured public projects

S/nProject typeFC. (mill.)IC. (mill.)Dev.% Dev.FT. (weeks)IT. (weeks)Dev.% Dev.
1Offices56.046.010.021.73224833.3
2Educational building4.54.50.00.04400.0
3Social building (ren.)1.51.00.550.04400.0
4Utility building4.54.50.00.06600.0
5Health care centre6.05.01.020.032201260.0
6Health care centre5.05.00.00.064250.0
7Educational building7.17.10.00.054125.0
8Social building (ren.)10.510.00.55.03224833.3
9Offices830.0830.00.00.03224833.3
10Social building (ren.)10.08.51.517.62824416.7
11Residential28.230.0−1.8−6.01718−1−5.6
12Educational building4.44.5−0.1−2.264250.0
Average1.08.8424.7