Construction mediation and its hybridization: the case of the Hong Kong construction industry


Cite

Fig. 1

Contracting parties and stakeholders of a construction project.
Contracting parties and stakeholders of a construction project.

Cost claim categories.

CategoryDescription
CC 1Ambiguity in documents
CC 2Construction method change due to Engineer’s comments (on Contractor’s method statement)
CC 3Error in setting out due to incorrect data shown on drawings
CC 4Rectification of damage caused by excepted risks
CC 5Disposal of fossils
CC 6Facilities provided to other contractors, in excess of those anticipated at the tender stage
CC 7Additional tests (to verify compliance with specifications, in excess of those anticipated at the tender stage)
CC 8Uncovering of works for examination
CC 9Delayed possession of works
CC 10Acceleration of works
CC 11Suspension of works
CC 12Additional work (to other parts of the works) arising from repairs or defects
CC 13Investigation of alleged defects
CC 14Interest on claims due to their late valuation
CC 15Disruption to regular progress due to :
  CC 15Alate instructions
  CC 15Bvariations
  CC 15Copening for inspection
  CC 15Ddelay caused by any person or organization employed by the Employer
  CC 15Elate delivery of materials by the Employer
CC 16Employer’s breach of contract
CC 17Variations (including Engineer’s instruction to change)
CC 18Other reasons
  CC 18A– Delay caused by additional/unforeseen government departmental procedures and late issue of consent
  CC 18B– Overbreaks on cutting slopes
  CC 18B+CC 18C– Delays caused by unforeseeable obstructions to foundation constructions
CC minor– Delays due to variations
– Incorporation of categories where claims were relatively “minor”

Time claim categories.

CategoryDescription
TC 1Inclement weather
TC 2Hoisting of typhoon signal no. 8 or above
TC 3Instruction issued to resolve discrepancy
TC 4Variation Order
TC 5Substantial increase in quantity of any work item not resulting from a variation
TC 6Delayed possession of site
TC 7Disruption to regular progress due to:
  TC 7Alate instructions
  TC 7Bvariations
  TC 7Copening for inspection
  TC 7Ddelay caused by any person or organization employed by the Employer
  TC 7Elate delivery of materials by the Employer
TC 8Suspension of works by the Employer
TC 9Delay caused by an utility services organization
TC 10Excepted risks
TC 11Any other special circumstances
  TC 11A– Disruption to regular progress due to additional/unforeseen government departmental procedures, or late consent
  TC 11B– Disruption to regular progress due to unforeseeable obstructions