Open Access

Project ambidexterity: case of recovering schedule delay in a brownfield airport project in India


Cite

Fig. 1

Overall research approach. PMBOK = Project Management Body of Knowledge; PMI = Project Management Institute.
Overall research approach. PMBOK = Project Management Body of Knowledge; PMI = Project Management Institute.

Fig. 2

Overview of the main terminal of the Netaji Subhas Chandra Bose International Airport at Kolkata, India.
Overview of the main terminal of the Netaji Subhas Chandra Bose International Airport at Kolkata, India.

Status of construction projects in airports operated by the AAI* (as on March 31, 2011).

No.LocationProject nameProject value (INR§, millions)Physical work completionTime overrun (as on March 31, 2011)
1AhmedabadConstruction of new International Terminal Building2,909100% (just commissioned)1 month
2ChennaiDevelopment of Terminal Building and pavement works5,35027%No delay reported
3ChennaiDevelopment of Kamaraj Domestic Terminal Phase-2, and expansion of Anna International Terminal Building12,73064%Delay reported, but not quantified
4ChennaiExtension of secondary runway, construction of taxi tracks2,32899.5%No delay reported
5ChennaiConstruction of RCC/prestressed concrete bridge across the River Adyar2,28099%No delay reported
6KolkataConstruction of Integrated Passenger Terminal Building at Netaji Subhas Chandra Bose International (NSCBI) Airport23,25063%3 months’ delay
7GangtokNew airport at Pakyong near Gangtok2,64338%17 months’ delay
8GoaConstruction of new International Terminal Building3,30016%Delay reported, but not quantified
9Multiple locationsGAGAN Project (the AAI in collaboration with the Indian Space Research Organization, for satellite-based navigation)3,93662.15%No delay reported

Examples of recent airport construction delays across the world*.

Serial No.CityCountryDescription
1DhakaBangladeshNew greenfield airport land acquisition issues resulting in non-commencement of project
2MuscatOmanDelays due to design modifications
3BrandenburgGermany6-year delay (original opening plan 2010, expected 2016); cost overrun of €1.2 billion; €80 million litigation for poor planning
4QuitoEcuador18-month delay; renegotiation, dispute resolution
5SantiagoChileRe-tendering, quantum of delay to be ascertained
6MalagaSpainEnvironment clearance delays; change in plans
7DurbanSouth AfricaRenovation required within 2 years due to poor design and restricted access
8ZagrebCroatia10-year planning; year-long tendering in 2011; construction started May 2014; expected completion December 2016; optimistic schedule
9DohaQatar6-month delay in opening to decide the main contractor becoming the airport operator
10IslamabadPakistan70% behind schedule, audit detected irregularity
11New KhartoumSudanMultiyear delay to finalize finances (Sudan suffered loss in State revenues due to partition)
12Campinas CityBrazilUnsafe working conditions; construction delay

Stages of the GT* study adopted for this research.

StagePurpose of the stage
Open codingCollection of granular text data, such as those from stakeholder interviews, project records. Identified data are tagged and sorted by key points, which have been termed “open codes”.
Selective codingCollection of open codes similar in concept, which allowed the data to be grouped into “anchors”
CategoriesBroad groups of similar concepts that are used to generate theory
TheoryA collection of similar explanations that explain the subject of the research

Description of key constraints, anchors, and categories, as well as their effects on project schedule.

Description of situation and constraintAnchor and categoryEffect on project and consequential delaysRank
Shifting of electrical substation; permission for demolition of link building. These were critical pieces of operational infrastructure located in Zone 1 of the proposed Integrated Terminal Building.Anchor: land encumbrance;category: site constraintLink building area was handed over on April 1, 2011, about 29 months after commencement of construction.1
Shifting of line maintenance building and motor transport workshop and permission for demolition. These were operational facilities located in Zones 3 and 4 of the proposed Integrated Terminal BuildingAnchor: land encumbrance;category: site constraintLine maintenance building area was handed over on October 20, 2009, about 1 year after commencement of construction.2
Service area, its building, and the underground sewerage treatment plant were not defined in the initial plan drawings.Anchor: land encumbrance;category: site constraintThe locations were finalized 1 year after commencement of construction.3
Inclusion of separate architect/design consultant for Domestic and International terminals, with no interface between the consultants, resulted in major disorder when the structure was designed as an integrated terminal.Anchor: cascading planning deficiency;category: process constraintDissimilar architectural concept and design outputs with convergence disagreements between consultants resulted in time loss. This time loss affected the schedule performance but could not be segregated and quantified in the study.4

The AAI had no prior experience of such a large commissioning exercise since its inception in 1994.

Transition of all operations staff, airlines, passenger, security, health organization, customs and passport control services. Operations from existing terminal buildings were planned to be shut down.

Anchor: complex, multidisciplinary decision-making environment;category: governance constraintAny glitch in transition would delay project commissioning. Other high-profile international airports experienced commissioning fiascos. Meticulous planning and rigorous trails ensured smooth transition, and hence this was picked up for detailed study.5
Without restricting appropriate access for existing airport operations, there was limited space available to be given to the contractor for setting up the fabrication yard, Concrete batching plant and its operations, and equipment storage. Maneuverability of equipment and vehicle were also constrained within the project area.Anchor: access restriction;category: site constraintLack of proper road network within the project area led to equipment underutilization and hindered movement of project resources. This, however, finally did not cause project delay.6
Rerouting of existing operational utilities, services, and communication cables from the project area in the absence of their detailed drawings. Most of these were serving the existing airport, and any inadvertent damage during excavation or other works would be potentially disruptive for airport operations.Anchor: knowledge of existing utilities network/layout;category: site constraintWhile this was a “known unknown”, it led to uncertainty with potential to affect schedule. This was managed by the AAI with additional efforts and emerged as a learning point from this study.7

There was a storm water pond in the project area, which needed to be filled up as a part of site preparation activity.

Rerouting of inlet to pond and its discharge into the existing drainage system of the civic authority

Anchor: reclamation of land/brownfield contamination;category: site constraintThough pond filling activity was planned, the rerouting of the inlet to pond was not initially budgeted. This was included as a revision, but finally, it did not delay the project.8
Location of operational aviation turbine fuel storage tank area near the project construction site (on the fringes of Zone 6). This required the following:

implementation of additional safety measures during construction

maintenance of access roads for tankers approaching from the city side to the fuel storage tank area throughout the construction period.

Anchor: land encumbrance;category: site constraintEfforts to get the fuel oil marketing firm to relocate their fuel storage tanks did not materialize and needed repeated changing of temporary access roads to allow tankers to reach the fuel storage tank area. No delay in project schedule.9
Lengthy organizational procedure for effecting any change in contract, such as Bill of Material, specifications, quantities, services, and other change orders that may become necessary during project execution.Anchor: organization procedural environment;category: governance constraintLayouts or numbers were required to be shared and agreed with the contractor to know the flexibility on the availability of material or substitutes and their construction viability before implementing the drawings for construction purposes. No delay in schedule.10

Assessing the underlying phenomenon in the schedule recovery measures.

#Constraint categoryPMI knowledge area applied for schedule recoverySchedule recovery measures and their underlying phenomenon
1Site constraint

Time management

Resource management

Claim management

Integration management

Managers moved away from conventional practices of activity scheduling to orchestrate all project resources and dynamically operated in a turbulent environment within less time, without sacrificing cost and quality, in addition to handling emergent claims effectively. The AAI intervened when needed to exploit prior in-house (or externally accessed) learning and explore new solutions by integrating stakeholders within the available time to deliver the project. All these steps demonstrated ambidexterity.
2Process constraint

Time management

Integration management

3Governance constraint

Time management

Resource management

Stakeholder management

Integration management

Mapping of anchors into categories.

AnchorCategory
Land encumbranceSite constraint
Access restriction
Knowledge of existing utilities network/layout
Reclamation of land/brownfield contamination
Cascading planning deficiencyProcess constraint
Complex, multidisciplinary decision-making environmentGovernance constraint
Organization procedural environment
eISSN:
1847-6228
Language:
English
Publication timeframe:
Volume Open
Journal Subjects:
Engineering, Introductions and Overviews, other