Open Access

Elimination of constraints in the production process of power equipment components and the analysis of the resulting benefits

   | Oct 07, 2019

Cite

The article presents the results regarding the elimination of constraints in the production process of a power equipment subassembly, a boiler chamber, together with an analysis of the benefits resulting from this, both financial and non-financial. The significance of bottlenecks in the production process, ways of its identification and limitations - in general - are presented. The article is a case-study of an attempt to eliminate the bottleneck in the production process of the boiler chamber, which turned out to be the process of drilling and marking-off, and work stations representing these processes. In order to eliminate the limitation, it was decided to replace the existing tracing and drilling work with a numerically controlled device - a boring machine moved from the liquidated department.. As a result, labor-intensive, manual chambers marking-off and the process of drilling holes with a smaller diameter drill have been eliminated. A number of benefits has been demonstrated resulting from the elimination of the bottleneck in the process, first of all, it was possible to reduce the duration of the marking-off and drilling operations and reduce the costs of the boiler chamber production process.