Preliminary estimate for reinforcement steel quantity in residential buildings

Open access

Abstract

The objective of this study was to develop prediction mathematical equations to compute reinforcement steel quantity in traditional residential buildings based on 158 sets of data collected in the West Bank in Palestine. The records related to the quantities were collected from consultancy firms that provide reinforced concrete design services. The data were collected for residential buildings up to four floors. Linear regression analysis was chosen to show the correlation between the included variables. The following variables were used in the regression models: quantity of reinforcement steel (dependent variable), structural element volume (independent variable) and floor area (independent variable). Fourteen models were developed; nine models were developed to compute the quantity of reinforcement steel in different structural elements: slabs, beams, columns and footings. The other five models were used to estimate the total steel quantity in a residential building. The coefficient of multiple determination (R2) of the developed models ranged from 0.70 to 0.82. This confirms a good correlation between the dependent and the independent variables. The accuracy of the developed models was tested using the mean absolute percentage error (MAPE) test. With MAPE values ranging from 21% to 36%, the results compare favourably with past research that indicated that accuracy between ±25% and ±50% at the early stages is acceptable. The results also show that the models built on structural element size have better accuracy than the models using floor area. Such types of equations are very useful, especially in their simplicity and ability to be handled by calculators or simple computer programmes.

References

  • Abu Hammad, A., Alhaj Ali, S., Sweis, G., & Bashir, A. (2008). Prediction model for construction cost and duration in Jordan. Jordan Journal of Civil Engineering, 2(3), 250-266.

  • Ahuja, H. N., Dozzi, S. P., & Abourisk, S. M. (1994). Project Management Techniques in Planning and Controlling Construction Projects. John Wiley and Sons, Inc., New York.

  • Bell, L. C., & Bozai, G. A. (1987). Preliminary cost estimating for highway construction projects. AACE Transactions, C.6.1-C.6.4.

  • Enshassi, A., Hallaq, K., & Mohamed, S. (2006). Causes of contractor’s business failure in developing countries: the case of Palestine. Journal of Construction in Developing Countries, 11(2), 1-14.

  • Enshassi, A., Mohamed, S., & Madi, I. (2007). Contractors’ perspectives towards factors affecting cost estimation in Palestine. Jordan Journal of Civil Engineering, 1(2), 186-193.

  • Holm, L., Schaufelberger, J., Griffin, D., & Cole, T. (2005). Construction Cost Estimating: Process and Practices. Pearson Education, Inc., New Jersey.

  • Jrade, A., & Alkass, S. (2007). Computer-integrated system for estimating the costs of building projects. Journal of Architectural Engineering, 13(4), 205-223.

  • Lowe, D. J., Emsley, M. W., & Harding, A. (2006). Predicting construction cost using multiple regression techniques. Journal of Construction Engineering and Management. 132(7), pp. 750-758.

  • Mahamid, I. (2011). Early cost estimating for road construction projects using multiple regression techniques. Australasian Journal of Construction Economics and Building, 11(4), pp. 78-101.

  • Mahamid, I. (2013). Frequency of time overrun causes in road construction in Palestine: Contractors’ view. Organization, Technology and Management in Construction: An International Journal, 5(1), pp. 720-729.

  • Mahamid, I. (2015). Factors affecting cost estimating accuracy: evidence from Palestinian construction projects. International Journal of Management Science and Engineering Management, 10(2), pp. 117-125.

  • Navon, R. (2005). Automated project performance control of construction projects. Automation in Construction, 14, pp. 467-476.

  • Palestinian Academic Society for the Study of International Affairs (PASSIA). (2002). Available at http://www.passia.org/.

  • Schexnayder, C. J., & Mayo, R. E. (2003). Construction Management Fundamentals. McGraw-Hill Higher Education, Boston, MA.

  • Sodikov, J. (2005). Cost estimation of highway projects in developing country: artificial neural network approach. Journal of the Eastern Asia Society for Transportation Studies, 6, pp. 1036-1047.

  • United Nation (UN) Committee on Trade and Development. (1994). Prospect for Sustained Development of the Palestinian Economy in the West Bank and Gaza, 1990 to 2010: A Qualitative Framework. UN, Geneva.

Organization, Technology and Management in Construction: an International Journal

Co-published with University of Zagreb, Faculty of Civil Engineering

Journal Information

Metrics

All Time Past Year Past 30 Days
Abstract Views 0 0 0
Full Text Views 45 45 32
PDF Downloads 9 9 7