An Analytical Study of Critical Factors Affecting Contractor Efficiency in Construction Projects in Indian Scenario

Open access

Abstract

Purpose: Recent studies show that lowest bidder tech­nique is mainly used in developing countries such as India to award a contract. It has been demonstrated that the lowest bid is not always the accurate one and can lead to cost overruns and time extensions amongst other prob­lems. The aim of this study was to investigate the critical factors impacting contractor’s efficiency in Indian con­struction projects. Research approach: A survey was sent to participants of construction projects awarded by the government with the lowest bidder technique in Uttar Pradesh, India. For further research, snowball sampling was used, and struc­tured interviews were conducted amongst experienced managers and engineers of these projects on both client’s and contractor’s side.Findings: It was observed that, to a greater extent, the delays were caused due to contractor’s opportunistic behaviour. The main findings are that new bidding meth­odologies are to be tested as they can lead to the choice of a more accurate and realistic bidder. In addition, subjec­tive evaluation components, such as schedule and work­force, should be reflected in contract award methods in addition to the cost criteria. Further studies should be per­formed on the choice of contract awarding methodology based on the project size and type. Originality value: The researcher’s focus was to analyze the influence of contracting methodologies and factors affecting contractor’s performance in lowest bid award project, where this is an area of least focus amongst researchers in the Indian subcontinent.

If the inline PDF is not rendering correctly, you can download the PDF file here.

  • Aitken A. & Paton R. A. (2017). The ‘t-shaped buyer’: A transactional perspective on supply chain relationships. Journal of Purchasing and Supply Management 23(4) pp. 280-289. doi:

    • Crossref
    • Export Citation
  • Asgari S. Awwad R. Kandil A. & Odeh I. (2016). Impact of considering need for work and risk on performance of construction contractors: An agent-based approach. Automation in Construction 65 pp. 9-20. doi:

    • Crossref
    • Export Citation
  • Asim M. Deep S. & Ahmad S. A. (2017a). Time impact study of real estate sector construction projects post application of lean principles for delay resolutions. Indian Journal of Science and Technology 8(82) pp. 89-99.

  • Asim M. Deep S. & Ahmad S. A. (2017b). Time impact study of real estate sector construction projects post application of lean principles for delay resolutions. International Journal of Civil Engineering and Technology 8(2) pp. 89-99.

  • Bai C. Rezaei J. & Sarkis J. (2017). Multicriteria green supplier segmentation. IEEE Transactions on Engineering Management 64(4) pp. 515-528.

  • Chang J.-R. (2015). Performance records system for public construction contractors-application of smooth roads project. Journal of Performance of Constructed Facilities 30(3) p. 06015004.

  • Chang J.-R. (2016). Performance records system for public construction contractors—application of smooth roads project. Journal of Performance of Constructed Facilities 30(3) doi:

    • Crossref
    • Export Citation
  • Chang J. (2017). The effects of buyer-supplier’s collab­oration on knowledge and product innovation. Industrial Marketing Management 65 pp. 129-143. doi:

    • Crossref
    • Export Citation
  • Damoah I. S. & Akwei C. (2017). Government project failure in Ghana: A multidimensional approach. International Journal of Managing Projects in Business 10(1) pp. 32-59.

  • Deep S. Asim M. & Ahmad S. A. (2017a). Earned value based liability calculation algorithm for schedule delays in construction projects. Indian Journal of Science and Technology 10(15) pp. 1-10.

  • Deep S. Asim M. & Khan M. K. (2017b). Review of various delay causing factors and their resolution by application of lean principles in India. Baltic Journal of Real Estate Economics and Construction Management 5(1) pp. 101-117.

  • Deep S. Jefferies M. & Gajendran T. (2017c). Resolving constraints in collaborative procurement through the lens of a portfolio purchasing model: A traditional literature review. Paper presented at the International Symposium on Frontiers of Infrastructure Finance Indian Institute of Technology Kharagpur.

  • Deep S. Khan M. B. Ahmad S. & Saeed A. (2017d). A study of various factors affecting contractor’s performance in lowest bid award construction projects. International Journal of Civil Engineering and Technology 8(2) pp. 28-33.

  • Deep S. Singh D. & Ahmad S. (2017e). A review of contract awards to lowest bidder in Indian construction projects via case based approach. Open Journal of Business and Management 5(1) pp. 159-168.

  • Dixit V. Chaudhuri A. & Srivastava R. K. (2017). Procurement scheduling in engineer procure construct projects: A comparison of three fuzzy modelling approaches. International Journal of Construction Management 18 pp. 1-18. doi:

    • Crossref
    • Export Citation
  • Doğan S. Z. Çalğici P. K. Arditi D. & Günaydin H. M. (2016). Critical success factors of partnering in the building design process. METU Journal of the Faculty of Architecture 32(2).

  • Dražić J. Peško I. Mučenski V. Dejić A. & Romanovich M. (2016). Evaluating contractors and offered structural solution. Procedia Engineering 165 pp. 898-905. doi:

    • Crossref
    • Export Citation
  • Elyamany A. & Abdelrahman M. (2010). Contractor performance evaluation for the best value of superpave projects. Journal of Construction Engineering and Management 136(5) pp. 606-614. doi:

    • Crossref
    • Export Citation
  • Elzomor M. & Parrish K. (2016). Investigating building construction process and developing a performance index. Procedia Engineering 145 pp. 211-218. doi:

    • Crossref
    • Export Citation
  • Erdogan S. A. Šaparauskas J. & Turskis Z. (2017). Decision making in construction management: AHP and expert choice approach. Procedia Engineering 172 pp. 270-276. doi:

    • Crossref
    • Export Citation
  • Eriksson P. E. (2010). Partnering: What is it when should it be used and how should it be implemented? Construction Management and Economics 28(9) pp. 905-917.

  • Gündüz M. Nielsen Y. & Özdemir M. (2012). Quantification of delay factors using the relative importance index method for construction projects in turkey. Journal of Management in Engineering 29(2) pp. 133-139.

  • Hatush Z. & Skitmore M. (1997). Assessment and evaluation of contractor data against client goals using pert approach. Construction Management & Economics 15(4) pp. 327-340.

  • Heesom D. Xiao H. and Proverbs D.G. (2003). The development of appropriate measurements for the international comparison of contractor performance. Paper presented at the Construction Research Congress. Available at http://ascelibrary.org/doi/ abs/10.1061/40671%282003%2919

  • Ibironke O. T. Oladinrin T. O. Adeniyi O. & Eboreime I. V. (2013). Analysis of non-excusable delay factors influencing contractors’ performance in Lagos state Nigeria. Journal of Construction in Developing Countries 18(1) pp. 53-72.

  • Ioannou P. G. & Leu S.-S. (1993). Average-bid method- competitive bidding strategy. Journal of Construction Engineering and Management 119(1) pp. 131-147.

  • Ishii N. Takano Y. & Muraki M. (2014). An order acceptance strategy under limited engineering man-hours for cost estimation in engineering-procurement-construction projects. International Journal of Project Management 32(3) pp. 519-528.

  • Israel G. D. (1992). Determining Sample Size. University of Florida Cooperative Extension Service Institute of Food and Agriculture Sciences EDIS Gainesville.

  • Jaafar M. Nuruddin A. R. & Bakar S. P. S. A. (2016). Managerial capabilities of housing developers: Building the competitive advantage of a firm. International Journal of Construction Management 16(1) pp. 27-38.

  • Jekale W. (2004). Performance for Public Construction Projects in Developing Countries: Federal Road and Educational Building Projects in Ethiopia. Thesis Norwegian University of Science & Technology.

  • Khan A. R. Deep S. & Asim M. (2017a). Analysis of maintenance records of construction equipments and their importance in minimizing equipments breakdown during project execution phase to lessen time overrun. International Journal of Civil Engineering and Technology 8(83) pp. 11-23.

  • Khan M. A. Deep S. Asim M. & Khan Z. R. (2017b). Quantization of risks involved in supply of ready mix concrete in construction industry in Indian scenario. International Journal of Civil Engineering and Technology 8(3) pp. 175-184.

  • Khan M. A. Srivastava S. D. Asim M. & Khan Z. R. (2017c). Quantization of risks involved in supply of ready mix concrete in construction industry in Indian scenario. International Journal of Civil Engineering and Technology 8(3) pp. 175-184.

  • Kotula M. Ho W. Dey P. K. & Lee C. K. M. (2015). Strategic sourcing supplier selection misalignment with critical success factors: Findings from multiple case studies in Germany and the United Kingdom. International Journal of Production Economics 166 pp. 238-247.

  • Latham S. M. (1994). Constructing the Team. HM Stationery Office London.

  • Lema M. (2006). Alternative Project Delivery Methods for Public Constructions: Cases in Oromia Region. Addis Ababa University Addis Ababa.

  • Leśniak A. (2015). Reliability assessment of research into contractors’ bidding decisions. Procedia Engineering 122 pp. 251-257. doi:

    • Crossref
    • Export Citation
  • Manu E. Ankrah N. Chinyio E. & Proverbs D. (2015). Trust influencing factors in main contractor and subcontractor relationships during projects. International Journal of Project Management 33(7) pp. 1495-1508. doi:

    • Crossref
    • Export Citation
  • Mathivathanan D. Kannan D. & Haq A. N. (2017). Sustainable supply chain management practices in Indian automotive industry: A multi-stakeholder view. Resources Conservation and Recycling 128(01) pp. 284-305. doi:

    • Crossref
    • Export Citation
  • Mishra D. Gunasekaran A. Papadopoulos T. & Hazen B. (2017). Green supply chain performance measures: A review and bibliometric analysis. Sustainable Production and Consumption 10 pp. 85-99.

  • Naoum S. & Egbu C. (2015). Critical review of procurement method research in construction journals. Procedia Economics and Finance 21 pp. 6-13. doi:

    • Crossref
    • Export Citation
  • Ng S. T. Luu D. T. Chen S. E. & Lam K. C. (2002). Fuzzy membership functions of procurement selection criteria. Construction Management and Economics 20(3) pp. 285-296. doi:

    • Crossref
    • Export Citation
  • Oduro-Owusu K. Fugar F. & Manteau K. (2010). Factors influencing construction worker job satisfaction in the Ghanaian construction industry. Unpublished MSc thesis KNUST.

  • Palaneeswaran E. & Kumaraswamy M. (2001). Recent advances and proposed improvements in contractor prequalification methodologies. Building and Environment 36(1) pp. 73-87.

  • Palaneeswaran E. & Kumaraswamy M. M. (2000). Contractor selection for design/build projects. Journal of Construction Engineering and Management 126(5) pp. 331-339.

  • Safa M. Shahi A. Haas C. T. Fiander-McCann D. Safa M. Hipel K. et al. (2015). Competitive intelligence (CI) for evaluation of construction contractors. Automation in Construction 59 pp. 149-157. doi:

    • Crossref
    • Export Citation
  • Sanderson M. Allen P. Gill R. & Garnett E. (2018) New models of contracting in the public sector: A review of alliance contracting prime contracting and outcome‐based contracting literature. Social Policy & Administration 52 pp. 1060-1083. https://doi.org/10.1111/spol.12322.

  • Sarker B. R. Egbelu P. J. Liao T. W. & Yu J. (2012). Planning and design models for construction industry: A critical survey. Automation in Construction 22 pp. 123-134.

  • Setiawan H. Erdogan B. & Ogunlana S. O. (2015). Proactiveness of contractors: A study of Indonesia. Procedia Engineering 125 pp. 60-67. doi:

    • Crossref
    • Export Citation
  • Shehu Z. & Akintoye A. (2010). Major challenges to the successful implementation and practice of programme management in the construction environment: A critical analysis. International Journal of Project Management 28(1) pp. 26-39. doi:

    • Crossref
    • Export Citation
  • Sinčić Ćorić D. Anić I.-D. Piri Rajh S. Rajh E. & Kurnoga N. (2017). Organizational buying decision approaches in manufacturing industry: Developing measures and typology. Journal of Business & Industrial Marketing 32(2) pp. 227-237.

  • Singh M. K. Deep S. & Banerjee R. (2017a). Risk management in construction projects as per Indian scenario. International Journal of Civil Engineering and Technology 8(83) pp. 127-136.

  • Singh M. K. Deep S. & Banerjee R. (2017b). Risk management in construction projects as per Indian scenario. International Journal of Civil Engineering and Technology 8(3) pp. 127-136.

  • Suprapto M. Bakker H. L. M. & Mooi H. G. (2015a). Relational factors in owner-contractor collaboration: The mediating role of teamworking. International Journal of Project Management 33(6) pp. 1347-1363. doi:

    • Crossref
    • Export Citation
  • Suprapto M. Bakker H. L. M. Mooi H. G. & Moree W. (2015b). Sorting out the essence of owner-contractor collab­oration in capital project delivery. International Journal of Project Management 33(3) pp. 664-683. doi:

    • Crossref
    • Export Citation
  • Wahaj M. Deep S. Dixit R. B. & Khan M. B. (2017a). A study of project success and procurement frameworks in Indian construction industry. International Journal of Civil Engineering and Technology 8(3) pp. 167-174.

  • Wahaj M. Deep S. Dixit R. B. & Khan M. B. (2017b). A study of project success and procurement frameworks in Indian construction industry. International Journal of Civil Engineering and Technology 8(83) pp. 167-174.

  • Walker D. H. Hampson K. & Peters R. (2002). Project alliancing vs project partnering: A case study of the Australian national museum project. Supply Chain Management: An International Journal 7(2) pp. 83-91.

  • Wang C. M. Xu B. B. Zhang S. J. & Chen Y. Q. (2016). Influence of personality and risk propensity on risk perception of Chinese construction project managers. International Journal of Project Management 34(7) pp. 1294-1304. doi:

    • Crossref
    • Export Citation
  • Wang T. Tang W. Qi D. Shen W. & Huang M. (2015). Enhancing design management by partnering in delivery of international epc projects: Evidence from Chinese construction companies. Journal of Construction Engineering and Management 142(4) p. 04015099.

  • Winch G. M. (2000). Institutional reform in British construction: Partnering and private finance. Building Research & Information 28(2) pp. 141-155.

  • Wong C. H. (2004). Contractor performance prediction model for the United Kingdom construction contractor: Study of logistic regression approach. Journal of Construction Engineering and Management 130(5) pp. 691-698. doi:

    • Crossref
    • Export Citation
  • Xiao H. & Proverbs D. (2003). Factors influencing contractor performance: An international investigation. Engineering Construction and Architectural Management 10(5) pp. 322-332.

  • Yang W. Gao Y. Li Y. Shen H. & Zheng S. (2017). Different roles of control mechanisms in buyer-supplier conflict: An empirical study from China. Industrial Marketing Management 65 pp. 144-156. doi:

    • Crossref
    • Export Citation
Search
Journal information
Metrics
All Time Past Year Past 30 Days
Abstract Views 0 0 0
Full Text Views 428 325 13
PDF Downloads 322 211 11