Continuous Improvements at Operator Level

Abstract

Few empirical studies have previously reported on the implementation of takt planning and utilizing Deming cycles (PDCA) to control construction workflows continuously. This paper presents a case study from the offshore renewable industry, closely related to construction. The paper aims to develop and evaluate a conceptual model combining takt planning and the Deming cycle within the offshore wind construction environment. The conceptual model has through interactions with construction experts been modified for a visual board implementation, covering two alternative processes with a fixed number of technicians per performing team. The knowledge base for the conceptual model is based on Takt planning implementation from the lean construction community and PDCA implementation from the lean production community. The main contribution of this paper is the development and evaluation of the conceptual model combining takt planning and the Deming cycle in a construction environment. This conceptual model has potential implications in the construction and refurbishment industry.

If the inline PDF is not rendering correctly, you can download the PDF file here.

  • Alla, A. A., Quandt, M., and Lütjen, M. (2013). Simulation-based aggregate installation planning of offshore wind farms. International Journal of Energy, 72, 23-30.

  • Backe, S., and Haugland, D. (2017). Strategic Optimization of Offshore Wind Farm Installation. In International Conference on Computational Logistics, Springer, Cham, Switzerland, 285-299.

  • Ballard, G. (1999). Improving Work Flow Reliability. In Proceedings of the 7th Annual Conference of the International Group for Lean Construction, Berkeley, USA, 275-286.

  • Ballard, G., and Howell, G. (1997). Shielding production from uncertainty. In Construction Congress V: Managing Engineered Construction in Expanding Global Markets, 126-133.

  • Ballard, H. G. (2000). The last planner system of production control. Doctoral dissertation, University of Birmingham, Unpublished.

  • Barlow, E., Tezcaner Ozturk, D., Day, S., Boulougouris, E., Revie, M., and Akartunali, K. (2014). An assessment of vessel characteristics for the installation of offshore wind farms. In Proc., International Conference on Marine Technology, ICMT 2014.

  • Barlow, E., Tezcaner Öztürk, D., Revie, M., Akartunalı, K., Day, A. H., and Boulougouris, E. (2018). A mixed-method optimisation and simulation framework for supporting logistical decisions during offshore wind farm installations. European Journal of Operational Research, 264(3), 894-906.

  • Chauhan, K., Peltokorpi, A., Seppänen, O., and Berghede, K. (2018). Combining Takt Planning With Prefabrication for Industrialized Construction. In Proc., 26th Annual Conference of the International Group for Lean Construction, Chennai, India, 848-857.

  • Creswell, J. W. (2014). Research design: qualitative, quantitative, and mixed methods approaches. SAGE, Los Angeles, USA.

  • Deming, W. E. (2000). The new economics: for industry, government, education. MIT Press, Cambridge, Mass.

  • Emdanat, S., Linnik, M., and Christian, D. (2016). A Framework for Integrating Takt Planning, Last Planner System and Labor Tracking. In Proc., 24th Annual Conference of the International Group for Lean Construction, Boston, USA.

  • Frandson, A., Berghede, K., and Tommelein, I. D. (2013). Takt Time Planning for Construction of Exterior Cladding. In Proc., 21th Annual Conference of the International Group for Lean Construction, Fortaleza, Brazil, 527-536.

  • Frandson, A., Berghede, K., and Tommelein, I. D. (2014). Takt-Time Planning and the Last Planner. Proc., 22nd Annual Conference of the International Group for Lean Construction, Oslo, Norway, 571-580.

  • Frandson, A., and Tommelein, I. D. (2014). Development of a takt-time plan: A case study. In Construction Research Congress 2014: Construction in a Global Network, 1646-1655.

  • Heinonen, A., and Seppänen, O. (2016). Takt Time Planning: Lessons for Construction Industry from a Cruise Ship Cabin Refurbishment Case Study. Proc., 24th Annual Conference of the International Group for Lean Construction, Boston, USA.

  • Hevner, A. R., March, S. T., Park, J., and Ram, S. (2004). Design science in information systems research. MIS Quarterly, 28(1), 75-105.

  • Irawan, C. A., Song, X., Jones, D., and Akbari, N. (2017). Layout optimisation for an installation port of an offshore wind farm. European Journal of Operational Research, 259(1), 67-83.

  • ISO (2015). International Organization for Standardization. Retrieved from https://www.iso.org/files/live/sites/isoorg/files/archive/pdf/en/iso9001-2015-process-appr.pdf on September 12, 2018.

  • Kenley, R., and Seppänen, O. (2010). Location-based management for construction: planning, scheduling and control. Spon Press, Abingdon, UK.

  • Koskela, L. (1999). Management of Production in Construction: A Theoretical View. In Proc., 7th Annual Conference of the International Group for Lean Construction, Berkeley, USA, 241-252.

  • Koskela, L., Tezel, A., and Tzortzopoulos, P. (2018). Why Visual Management? In Proc., 26th Annual Conference of the International Group for Lean Construction, Chennai, India, 250-260.

  • Lacal-Arántegui, R., Yusta, J. M., and Domínguez-Navarro, J. A. (2018). Offshore wind installation: Analysing the evidence behind improvements in installation time. Renewable and Sustainable Energy Reviews, 92, 133-145.

  • Liker, J. K. (2004). The Toyota way: 14 management principles from the world’s greatest manufacturer. McGraw-Hill, New York, USA.

  • Liker, J. K., and Meier, D. (2006). The Toyota way fieldbook: a practical guide for implementing Toyota’s 4Ps, McGraw-Hill, New York, USA.

  • Peltokorpi, A., Olivieri, H., Granja, A. D., and Seppänen, O. (2018). Categorizing modularization strategies to achieve various objectives of building investments. Construction Management and Economics, 36(1), 32-48.

  • Seppänen, O. (2014). A Comparison of Takt Time and LBMS Planning Methods. Proc., 22nd Annual Conference of the International Group for Lean Construction, Oslo, Norway, 727-738.

  • Simon, H. A. (1996). The sciences of the artificial, MIT Press, London, England.

  • Thomas, H. R., Mathews, C. T., and Ward, J. G. (1986). Learning curve models of construction productivity. Journal of construction engineering and management, 112(2), 245-258.

  • Tommelein, I. D., and Riley, D. R. (1999). Parade game: Impact of work flow variability on trade performance. Journal of Construction Engineering & Management, 125(5), 304.

  • Ursavas, E. (2017). A benders decomposition approach for solving the offshore wind farm installation planning at the North Sea. European Journal of Operational Research, 258(2), 703-714.

  • Yin, R. K. (2014). Case study research: design and methods, Los Angeles, SAGE.

OPEN ACCESS

Journal + Issues

Search